easy way to calculate rate analysis of rcc work

Rate analysis for RCC work is essentially the method used to figure out how much it will cost to build a certain amount of reinforced cement concrete structure. It involves calculating expenses for materials, labor, and other necessary costs involved in the construction process.

rate analysis of rcc work

Given,

volume of rcc = 10m^3

mix ratio = 1:2:4

material rate analysis

Quantity

Total volume = 10m^3

Dry volume = 1.54*10 = 15.4m^3

ratio = 1:2:4

sum of ratio = 1+2+4 = 7

cement volume = (1/7)*15.4 = 2.2m^3

sand volume = (2/7)*15.4 = 4.4m^3

aggregate volume = (4/7)*15.4 = 8.8m^3

Cement quantity = 2.2*(1440/50) = 63.36 ~ 64bags

sand quantity = 4.4*35.32 = 155.4 ~ 156cft

aggregate quantity = 8.8*35.32 = 310.8 ~ 311cft

cost

Rate Assumptions:

cement/bag = ₹ 500

sand/cft = ₹ 12

aggregate/cft = ₹ 15

Amount

cement = 64*500 = ₹ 32000

sand = 156*12 = ₹ 1872

aggregate = 311*15 = ₹ 4665

Material cost

Sl. No.MaterialQuantityUnitRateAmount (₹)
1cement64bags50032000
2sand156cft121872
3aggregate311cft154665
Total₹ 38537

labour rate analysis

Labour Assumption

assuming the work to be completed in one day

No. of men required for the work

Head Mason = 2

Mason = 4

skilled labour =15

unskilled labour = 6

black smith = 3

carpenter = 4

water carrier = 3

Rate for men required

Head Mason = ₹ 1200

Mason = ₹ 1000

skilled labour = ₹ 800

unskilled labour = ₹ 500

black smith = ₹ 800

carpenter = ₹ 800

water carrier = ₹ 400

Amount

Head Mason = 1200*2 = ₹ 2400

Mason = 1000*4 = ₹ 4000

skilled labour = 800*15 = ₹ 12000

unskilled labour = 500*6 = ₹ 3000

black smith = 800*3 = ₹ 2400

carpenter = 800*4 = ₹ 3200

water carrier = 400*2 = ₹ 800

T&P (tools & plants) = ₹ 1000

Labour cost

Sl. No.DescriptionNo. of menDays requiredRateAmount (₹)
1Head Mason2112002400
2Mason4110004000
3skilled labour15180012000
4unskilled labour615003000
5black smith318002400
6carpenter418003200
7water carrier21400800
8T&P (tools & plants)10001000
Total₹ 28800

Total Cost = 38537+28800 = ₹ 67337

Add 1.5% water charges of total cost = 67337*0.015 = 1010

Add 10% contractor profit = 67337*0.1 = 6733.7 ~ 6734

Grand Total = 67337+1010+6734 = ₹ 75081

For 10m^3 of rcc work = ₹ 75081

Rate for rcc work will be 75081/10 = ₹ 7508/m^3

Note

The above calculation is the estimated but in practical amount may vary according to the machinery required, matrial cost, labour cost & site condition